Current Projects >> Honesdale Hospitality Site - Milestones
As expected, the hospitality site requires fairly complex and extensive survey, engineering and permitting processes. Route 6 Development began the feasibility analysis in 2004 and executed a purchase agreement in July 2005.
Some key milestones thus far have been:
| PKF marketing study and cash flow completed | June 2004 |
| Purchase agreement signed | July 2005 |
| Topographic analysis completed | Aug. 2005 |
| Title search completed | Mar. 2006 |
| Traffic Count completed | Aug. 2006 |
| PKF marketing study and cash flow updated | Feb. 2007 |
| Met w/Texas Township and Honesdale sewer authorities | May 2007 |
| Verbal agreement w/adjacent landowners re: emergency access road | June 2007 |
| Concept meeting w/township engineer | July 2007 |
| Submit preliminary plan to Texas Township PC | Sept. 2007 |
| Agreements w/Home Depot & Wal-Mart re: road access | Oct. 2007 |
| Submit National Pollutant Discharge Elimination System permit to PA DEP | Dec. 2007 |
| Complete traffic studies | Jan. 2008 |
| Submit HOP application | Jan. 2008 |
| Approval by Texas Township Board of Supervisors | Jan. 2008 |